Identified - The local power authority has issued a notice to curtail. The mining facility will power down between 2:00 PM to 10:00 PM Central Time on July 1st.

Our technicians will bring miners back online as soon as the curtailment period is complete. Thank you for your patience and understanding.

Jul 01, 2025 - 12:39 UTC
Update - Power has been restored at our Texas 6 facility. We'll continue to monitor the units to ensure stability.

We appreciate your patience and understanding.

May 09, 2025 - 15:06 UTC
Update - Our Texas 6 facility is currently experiencing an outage due to extreme weather conditions.
The main transformer tripped causing power loss to 18 containers. Onsite technicians are working to fix the issue.

We appreciate your patience and cooperation.

May 08, 2025 - 17:05 UTC
Update - The Transformer issue has been resolved. Currently, one container is affected by an on-going network maintenance.
Our team is working to bring the units in each container back online.

We appreciate your patience and cooperation.

May 07, 2025 - 12:13 UTC
Update - Texas 6 is currently experiencing a site-wide outage due to ongoing repairs related to a transformer issue. A site-wide shutdown is necessary to ensure safety during the repair process.

We appreciate your continued patience.

May 07, 2025 - 02:29 UTC
Update - Only 4 containers are now affected by the transformer outage.
We’ve identified the impacted containers and are working with the onsite team to bring the miners back online.

We appreciate your patience and cooperation.

May 06, 2025 - 14:19 UTC
Update - One of the main transformers at the substation is down, causing a power loss to 10 containers. An electrician is scheduled to inspect the issue today. We’ll continue to provide updates as we learn more.

We appreciate your patience and understanding as we work to resolve this issue.

May 05, 2025 - 19:30 UTC
Monitoring - Our Texas 6 onsite technicians are continuing to troubleshoot and diagnose offline/underhashing miners.

We appreciate your patience and cooperation.

Apr 25, 2025 - 17:41 UTC
Update - All miners have been moved from the container affected by the down transformer.
Onsite technicians are continuing to work through and troubleshoot miners and perform site maintenance to improve overall performance.

Mar 25, 2025 - 16:27 UTC
Identified - A transformer repair is ongoing affecting a subset of units in the facility.

Routine electrical maintenance and testing will begin the week of February 17.

This will cause intermittent downtime while technicians work through testing the site.

Feb 14, 2025 - 20:03 UTC
Update - The majority of miners have successfully relocated to other facilities, with fewer than 30 still in the process.
Jun 10, 2025 - 13:07 UTC
Monitoring - Almost all Texas 1 miners have been relocated. The remaining ~500 units will soon be shipped out for redeployment to other hosting facilities.
Mar 27, 2025 - 19:13 UTC
Identified - In preparation for our exit from the Texas 1 facility, we have begun winding down operations and relocating miners to another Compass facility in the U.S. The estimated timeline for completion is 6-9 weeks.

We anticipate that relocated miners will begin coming online at their new facility starting in January 2025.
Our team will let you know as soon as your miner is operational in its new location.

We appreciate your cooperation and understanding during this transition.

Nov 11, 2024 - 09:57 UTC
Update - Facility update: The Ohio 2 Facility identified a faulty transformer on a portion of the site (C2). Another portion of the site (C9) remains under maintenance. We apologize for the inconvenience, but our site team is on standby to bring the miners back online as soon as this is resolved. We appreciate your patience and cooperation.
Jun 04, 2025 - 13:09 UTC
Monitoring - Facility update: Repairs are done in the C2 container, and miners should return to hashing. The C9 container continues to undergo maintenance. Thank you for your patience and understanding.
Jun 03, 2025 - 14:24 UTC
Identified - Our Ohio 2 facility is experiencing issues with exhaust fans (C2) and ongoing maintenance on a portion of the site (C9). The onsite team will bring the miners back online as soon as this is resolved. We appreciate your patience and cooperation.
May 12, 2025 - 12:50 UTC
Identified - We are currently compiling all miners that are ready to be shipped from Canada to the U.S. While there is no confirmed ETA yet, we are in the process of finalizing the shipment list. This batch will include miners from customers who opted for relocation and have signed the waiver. We have sent follow-up communications to customers who have not yet signed the waiver in order to include them in the shipment schedule.

For customers still waiting on the miner swap offer, we will provide further updates once the swap units are available and the offers have been added to their respective accounts.

We appreciate your cooperation and understanding during this transition.

May 06, 2025 - 14:44 UTC

About This Site

Facility and Deployment Updates


To learn about your miner deployment status and our facilities, checkout out the latest Compass Mining Facility Update.

To find out where your miners are hosted and learn more about each facility, check out our Facility Details page.

Example miner workername: tx1abcd
tx1 = Facility Location - Texas 1
abcd = Unique ID for your miner. Can be seen on your Compass Dashboard.

Below you will find the current and historical status of our mining facilities.


Facilities will display as orange or yellow if there is facility-wide downtime. Facility downtime may be caused by planned or unplanned maintenance, power outages, or network outages. Issues for individual ASIC machines are not shown on this page.

You can check out our Mining Facilities.

If you have an ASIC offline and your facility is not under maintenance, please submit a request.

Indiana 1, United States ? Operational
Indiana 2, United States ? Operational
Iowa 2, United States Operational
Iowa 3, United States Operational
90 days ago
97.54 % uptime
Today
Iowa 4, United States Major Outage
90 days ago
93.75 % uptime
Today
Manitoba 2, Canada ? Major Outage
Manitoba 4, Canada ? Operational
Manitoba 5, Canada ? Operational
Manitoba 6, Canada Operational
Manitoba 7, Canada ? Operational
Manitoba 8, Canada ? Operational
Manitoba 9, Canada Major Outage
Minnesota, United States ? Operational
Nebraska 2, United States Operational
90 days ago
97.05 % uptime
Today
North Dakota, United States Operational
90 days ago
97.48 % uptime
Today
Ohio 2, United States Partial Outage
Ontario, Canada ? Operational
Texas 5, United States Operational
Texas 6, United States Operational
90 days ago
98.13 % uptime
Today
Operational
Degraded Performance
Partial Outage
Major Outage
Maintenance
Major outage
Partial outage
No downtime recorded on this day.
No data exists for this day.
had a major outage.
had a partial outage.
Jul 1, 2025

Unresolved incident: Iowa 4 - Scheduled Power Curtailment.

Jun 30, 2025
Resolved - This incident has been resolved.
Jun 30, 23:26 UTC
Identified - The local power authority has issued a notice to curtail. The mining facility will power down, and our technicians will bring miners back online as soon as the curtailment period is complete. Thank you for your patience and understanding.
Jun 30, 18:22 UTC
Resolved - This incident has been resolved.
Jun 30, 05:24 UTC
Identified - The local power authority has issued a notice to curtail. The mining facility will power down between the hours of 6:00 PM CDT – 8:00 PM CDT, June 29th. Our technicians will bring miners back online as soon as the curtailment period is complete. Thank you for your patience and understanding.
Jun 29, 01:24 UTC
Jun 29, 2025
Resolved - This incident has been resolved.
Jun 29, 13:17 UTC
Update - We are continuing to work on a fix for this issue.
Jun 29, 13:17 UTC
Identified - The Minnesota facility will undergo a scheduled curtailment today, June 28th, from 5:00 PM to 11:00 PM Central Time. There is a possibility that the curtailment may start early or may be extended. Once power is restored, the onsite team will promptly bring the miners back online. We appreciate your patience and understanding.
Jun 28, 11:23 UTC
Jun 28, 2025
Jun 27, 2025
Completed - The scheduled maintenance has been completed.
Jun 27, 21:09 UTC
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jun 27, 18:00 UTC
Scheduled - The Ohio 2 facility is undergoing curtailment today from 2:00 PM to 7:00 PM EST. Once power is restored, the onsite team will promptly bring the miners back online. We appreciate your patience and understanding.
Jun 27, 16:45 UTC
Resolved - This incident has been resolved.
Jun 27, 05:41 UTC
Identified - The Minnesota facility will undergo a scheduled curtailment today, June 26th, from 6:00 PM to 9:00 PM Central Time. There is a possibility that the curtailment may be extended. Once power is restored, the onsite team will promptly bring the miners back online. We appreciate your patience and understanding.
Jun 26, 09:07 UTC
Resolved - This incident has been resolved.
Jun 27, 05:40 UTC
Identified - The power provider at our Indiana 1 and Indiana 2 facilities scheduled a curtailment today, June 26, 2025.

We will have an outage from 4:30 PM to 8:00 PM EST, lasting approximately 3 ½ to 4 hours.

We apologize for any inconvenience this may cause and appreciate your understanding as we work to comply with the demands of the power grid.

Thank you for your patience and kind understanding.

Jun 26, 13:04 UTC
Resolved - This incident has been resolved.
Jun 27, 05:39 UTC
Identified - Due to peak grid demand, the Midcontinent Independent System Operator (MISO) has issued a notice to curtail. The mining facility will curtail between the hours of 4:00 PM to 10:00 PM Central Time on June 26. Our technicians will bring miners back online as soon as possible. Thank you for your patience and understanding.
Jun 26, 13:47 UTC
Completed - The scheduled maintenance has been completed.
Jun 27, 00:00 UTC
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jun 26, 17:00 UTC
Scheduled - The Ohio 2 facility is undergoing curtailment today from 1:00 PM to 8:00 PM EST. Once power is restored, the onsite team will promptly bring the miners back online. We appreciate your patience and understanding.
Jun 26, 15:11 UTC
Jun 26, 2025
Resolved - This incident has been resolved.
Jun 26, 04:19 UTC
Identified - Due to peak grid demand, the Midcontinent Independent System Operator (MISO) has issued a notice to curtail. The mining facility will curtail between the hours of 3:00 PM to 9:00 PM Central Time on June 25. Our technicians will bring miners back online as soon as possible. Thank you for your patience and understanding.
Jun 25, 12:50 UTC
Resolved - This incident has been resolved.
Jun 26, 04:17 UTC
Identified - The power provider at our Indiana 1 and Indiana 2 facilities scheduled a curtailment today, June 25, 2025.

We will have an outage from 4:30 PM to 8:00 PM EST, lasting approximately 3 ½ to 4 hours.

We apologize for any inconvenience this may cause and appreciate your understanding as we work to comply with the demands of the power grid.

Thank you for your patience and kind understanding.

Jun 25, 16:02 UTC
Completed - The scheduled maintenance has been completed.
Jun 26, 02:00 UTC
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jun 25, 22:00 UTC
Scheduled - Our Iowa 2 and Iowa 3 facilities are scheduled to curtail today, June 25, 2025, for 4 hours, from 5:00 PM to 9:00 PM Central Time. The onsite team will bring the miners back online as soon as power is fully restored. We appreciate your patience and cooperation during this time.
Jun 25, 15:56 UTC
Completed - The scheduled maintenance has been completed.
Jun 26, 00:00 UTC
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jun 25, 17:00 UTC
Scheduled - The Ohio 2 facility is undergoing curtailment today from 1:00 PM to 8:00 PM EST. Once power is restored, the onsite team will promptly bring the miners back online. We appreciate your patience and understanding.
Jun 25, 15:33 UTC
Jun 25, 2025
Resolved - This incident has been resolved.
Jun 25, 14:22 UTC
Identified - Due to the ongoing extreme heatwave impacting the site, the Minnesota facility will undergo a mandatory curtailment today, June 24th, from 11:00 AM to 10:00 PM Central Time. This schedule is subject to change based on evolving grid demands.

Our onsite team is prepared to promptly restore operations and bring the miners back online as soon as power becomes available.

We sincerely appreciate your continued patience and understanding during this time.

Jun 24, 10:03 UTC
Resolved - This incident has been resolved.
Jun 25, 13:14 UTC
Identified - The power provider at our Indiana 1 and Indiana 2 facilities scheduled a curtailment today, June 24, 2025.

We will have an outage from 4:30 PM to 8:00 PM EST, lasting approximately 3 ½ to 4 hours.

We apologize for any inconvenience this may cause and appreciate your understanding as we work to comply with the demands of the power grid.

Thank you for your patience and kind understanding.

Jun 24, 12:03 UTC
Resolved - This incident has been resolved.
Jun 25, 07:13 UTC
Update - Sites 1, 1-B, and 3 are also curtailing today for 11 hours, starting from 11:00 AM to 10:00 PM Central Time.
Jun 24, 16:09 UTC
Identified - Sites 2 and 6 are curtailing today, June 24, 2025, for 13 hours, starting from 10 AM to 11 PM Central Time. The onsite team will bring the miners back online as soon as power is fully restored. We appreciate your patience and cooperation.
Jun 24, 15:46 UTC
Resolved - This incident has been resolved.
Jun 25, 05:17 UTC
Identified - Due to peak grid demand, the Midcontinent Independent System Operator (MISO) has issued a notice to curtail. The mining facility will curtail between the hours of 4:00 PM to 10:00 PM Central Time on June 23. Our technicians will bring miners back online as soon as possible. Thank you for your patience and understanding.
Jun 23, 15:39 UTC
Completed - The scheduled maintenance has been completed.
Jun 25, 00:53 UTC
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jun 24, 16:23 UTC
Scheduled - The Ohio 2 facility is undergoing curtailment today until 9:00 PM EST. Once power is restored, the onsite team will promptly bring the miners back online. We appreciate your patience and understanding.
Jun 24, 16:21 UTC
Jun 24, 2025
Resolved - This incident has been resolved.
Jun 24, 10:28 UTC
Identified - High winds at our Nebraska 2 facility are pushing hot air back into the building by forcing against the exhaust fans. This is affecting airflow and causing elevated temperatures, impacting 714 miners.

The issue is weather-related. Our team is monitoring the situation closely and working to minimize the impact.

Jun 23, 07:30 UTC
Investigating - We are currently investigating this issue.
Jun 21, 04:48 UTC
Resolved - This incident has been resolved.
Jun 24, 10:07 UTC
Identified - The power provider at our Indiana 1 and Indiana 2 facilities scheduled a curtailment today, June 23, 2025.

We will have an outage from 4:30 PM to 8:00 PM EST, lasting approximately 3 ½ to 4 hours.

We apologize for any inconvenience this may cause and appreciate your understanding as we work to comply with the demands of the power grid.

Thank you for your patience and kind understanding.

Jun 23, 14:22 UTC
Resolved - This incident has been resolved.
Jun 24, 05:01 UTC
Update - The site is still curtailing due to the persistent heat wave. We appreciate your patience and cooperation.
Jun 23, 04:08 UTC
Identified - The Minnesota is currently curtailing due to the heat coming this weekend. We will share updates as they become available. Once power is restored, our onsite team will work swiftly to bring the miners back online. We appreciate your continued patience and understanding.
Jun 22, 04:56 UTC
Resolved - This incident has been resolved.
Jun 24, 04:58 UTC
Update - We are continuing to work on a fix for this issue.
Jun 24, 04:58 UTC
Identified - Due to peak grid demand, the Midcontinent Independent System Operator (MISO) has issued a notice to curtail. The mining facility will curtail between the hours of 4PM and 10PM CST on Sunday, June 22. Our technicians will bring miners back online as soon as possible. Thank you for your patience and understanding.
Jun 23, 01:38 UTC
Completed - The scheduled maintenance has been completed.
Jun 24, 04:00 UTC
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jun 23, 18:00 UTC
Scheduled - Iowa 2 and 3 facilities will be curtailing today, June 23, 2025. Sites 2 and 6 will be curtailing from 1:00 PM CDT to 11:00 PM CDT. Sites 1, 1-B, and 3 are also curtailing from 2:00 PM CDT – 11:00 PM CDT.

The onsite team will bring the miners back online as soon as power is fully restored. We appreciate your patience and cooperation.

Jun 23, 16:02 UTC
Completed - The scheduled maintenance has been completed.
Jun 24, 00:00 UTC
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jun 23, 16:00 UTC
Scheduled - The Ohio 2 facility will undergo a scheduled curtailment today from 12:00 PM to 8:00 PM EST.

There is a possibility that the curtailment may be extended. Once power is restored, the onsite team will promptly bring the miners back online. We appreciate your patience and understanding.

Jun 23, 14:43 UTC
Jun 23, 2025
Resolved - This incident has been resolved.
Jun 23, 13:05 UTC
Identified - Iowa 2 and Iowa 3 is currently curtailing. The onsite team will bring the miners back online as soon as power is fully restored. We appreciate your patience and cooperation.
Jun 22, 03:08 UTC
Jun 22, 2025
Jun 21, 2025
Resolved - This incident has been resolved.
Jun 21, 09:18 UTC
Identified - Minnesota facility will undergo curtailment today, June 20th, from 2:00 PM to 8:00 PM Central Time.

A severe heat wave is forecasted to impact the Midwest this weekend, with temperatures expected to reach the high 90s. We will share updates as they become available. Once power is restored, our onsite team will work swiftly to bring the miners back online.

We appreciate your continued patience and understanding.

Jun 20, 12:42 UTC
Resolved - This incident has been resolved.
Jun 21, 09:08 UTC
Identified - Iowa 3 is currently curtailing. The onsite team will bring the miners back online as soon as power is fully restored.
Jun 20, 20:09 UTC
Resolved - This incident has been resolved.
Jun 21, 05:19 UTC
Identified - The Texas 6 facility is currently undergoing a curtailment. The onsite team will bring the miners back online once power is fully restored. We appreciate your patience and cooperation.
Jun 19, 22:01 UTC
Jun 20, 2025
Resolved - This incident has been resolved.
Jun 20, 11:30 UTC
Identified - The Minnesota facility will undergo a scheduled curtailment today, June 19th, from 2:00 PM to 6:00 PM Central Time.

There is a possibility that the curtailment may be extended. Once power is restored, the onsite team will promptly bring the miners back online. We appreciate your patience and understanding.

Jun 19, 19:55 UTC
Jun 19, 2025
Completed - The scheduled maintenance has been completed.
Jun 19, 18:50 UTC
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jun 19, 15:50 UTC
Scheduled - The Nebraska 2 facility is undergoing electrical maintenance affecting 2/3 of the site. The onsite team will bring the miners back online as soon as this is completed and power is fully restored. We appreciate your patience and cooperation.
Jun 19, 15:49 UTC
Completed - The scheduled maintenance has been completed.
Jun 19, 17:35 UTC
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jun 19, 16:35 UTC
Scheduled - Our Ohio 2 facility has ongoing maintenance on a portion of the site (C6), troubleshooting fan motors. The onsite team will bring the miners back online as soon as power is fully restored. We appreciate your patience and cooperation.
Jun 19, 16:33 UTC
Resolved - This incident has been resolved.
Jun 19, 12:19 UTC
Investigating - We are currently investigating this issue.
Jun 19, 06:14 UTC
Resolved - This incident has been resolved.
Jun 19, 06:11 UTC
Identified - The Texas 6 site has curtailed for 4CP peak demand.

Power will be restored by onsite technicians as soon as possible.

Jun 18, 21:10 UTC
Resolved - This incident has been resolved.
Jun 19, 05:53 UTC
Investigating - We’re currently experiencing a power issue affecting 36 units in one of our racks. Our team is actively working to resolve the issue and restore service as quickly as possible.

We appreciate your patience and cooperation.

Jun 18, 06:27 UTC
Jun 18, 2025
Resolved - This incident has been resolved.
Jun 18, 08:52 UTC
Investigating - We are currently investigating this issue.
Jun 18, 07:50 UTC
Resolved - This incident has been resolved.
Jun 18, 05:03 UTC
Update - Iowa 2 and Iowa 3 is currently curtailing. The onsite team will bring the miners back online as soon as power is fully restored.
We appreciate your cooperation.

Jun 18, 02:23 UTC
Identified - The issue has been identified and a fix is being implemented.
Jun 18, 02:21 UTC
Resolved - This incident has been resolved.
Jun 18, 04:22 UTC
Identified - The power provider at our Indiana 1 and Indiana 2 facility scheduled a curtailment today, June 17, 2025.

We will have an outage from 4:30 PM to 8:00 PM EST, lasting approximately 3 ½ to 4 hours.

We apologize for any inconvenience this may cause and appreciate your understanding as we work to comply with the demands of the power grid.

Thank you for your cooperation.

Jun 17, 13:56 UTC
Jun 17, 2025
Resolved - This incident has been resolved.
Jun 17, 13:40 UTC
Identified - The power provider at our Indiana 1 and Indiana 2 facility scheduled a curtailment today, June 16, 2025.

We will have an outage from 4:30 PM to 8:00 PM EST, lasting approximately 3 ½ to 4 hours.

We apologize for any inconvenience this may cause and appreciate your understanding as we work to comply with the demands of the power grid.

Thank you for your cooperation.

Jun 16, 14:11 UTC
Resolved - This incident has been resolved.
Jun 17, 12:13 UTC
Identified - The Minnesota facility will undergo a scheduled curtailment today, June 16th, from 2:00 PM to 6:00 PM Central Time.

There is a slight possibility that the curtailment may be extended. Once power is restored, the onsite team will promptly bring the miners back online. We appreciate your patience and understanding.

Jun 16, 16:27 UTC