Identified - The local power authority has issued a notice to curtail. The mining facility will power down between 7:00 AM to 9:00 AM and 5:00 PM to 7:00 PM Central time, February 23, 2026.

Our technicians will bring miners back online as soon as the curtailment period is complete. Thank you for your patience and understanding.

Feb 23, 2026 - 06:10 UTC
Identified - The local power authority has issued a notice to curtail. The mining facility will power down between 6:00 AM to 9:00 AM and 4:00 PM to 10:00 PM Central time, February 23, 2026.

Our technicians will bring miners back online as soon as the curtailment period is complete. Thank you for your patience and understanding.

Feb 23, 2026 - 06:08 UTC
Update - The facility relocation remains in progress. Unit activations are underway, and several units are already coming online at the new facility.

Thank you for your continued patience and understanding.

Feb 05, 2026 - 13:37 UTC
Monitoring - We wanted to share an update regarding the Ohio 2 facility. The relocation process is currently underway, and miners at this location are being safely powered down in preparation for transfer to a new hosting facility in Texas 8.

672 miners have already been uninstalled and will arrive in Texas 8 this week. These units will be energized as soon as possible.

Temporary miners have been assigned based on availability.

We understand this transition may cause temporary disruption, and we truly appreciate your patience and understanding. Once your miners have been relocated and brought back online, our Remote Operations team will notify you right away.

Thank you for your continued cooperation. Our team remains available should you need any assistance.

Jan 05, 2026 - 16:26 UTC
Identified - Miners from the Texas 6 facility are being relocated to a more optimal site to enhance uptime. The relocation process is currently underway. Provided there are no unforeseen delays, miners are expected to be online at a new Compass Mining facility by October 15, 2025. Our team is currently working through providing miner swaps for customers who elected this option.
Sep 08, 2025 - 13:49 UTC
Identified - We are currently compiling all miners that are ready to be shipped from Canada to the U.S. While there is no confirmed ETA yet, we are in the process of finalizing the shipment list. This batch will include miners from customers who opted for relocation and have signed the waiver. We have sent follow-up communications to customers who have not yet signed the waiver in order to include them in the shipment schedule.

For customers still waiting on the miner swap offer, we will provide further updates once the swap units are available and the offers have been added to their respective accounts.

We appreciate your cooperation and understanding during this transition.

May 06, 2025 - 14:44 UTC

About This Site

Facility and Deployment Updates


To learn about your miner deployment status and our facilities, checkout out the latest Compass Mining Facility Update.

To find out where your miners are hosted and learn more about each facility, check out our Facility Details page.

Example miner workername: tx1abcd
tx1 = Facility Location - Texas 1
abcd = Unique ID for your miner. Can be seen on your Compass Dashboard.

Below you will find the current and historical status of our mining facilities.


Facilities will display as orange or yellow if there is facility-wide downtime. Facility downtime may be caused by planned or unplanned maintenance, power outages, or network outages. Issues for individual ASIC machines are not shown on this page.

You can check out our Mining Facilities.

If you have an ASIC offline and your facility is not under maintenance, please submit a request.

Indiana 1, United States Operational
Indiana 2, United States Operational
Iowa 2, United States Operational
Iowa 3, United States Operational
Iowa 4, United States Operational
Manitoba 2, Canada Major Outage
Manitoba 4, Canada Operational
Manitoba 5, Canada Operational
Manitoba 6, Canada Operational
Manitoba 7, Canada Operational
Manitoba 8, Canada Operational
Manitoba 9, Canada Major Outage
Minnesota 1, United States Major Outage
Minnesota 2, United States Major Outage
North Dakota, United States Operational
Ohio 2, United States Under Maintenance
Ontario, Canada Operational
Texas 5, United States Operational
Indiana 3 Operational
Texas 5 (2) Operational
Texas 8 Operational
Operational
Degraded Performance
Partial Outage
Major Outage
Maintenance
Feb 23, 2026

Unresolved incidents: Minnesota 2 - Scheduled Power Curtailment, Minnesota 1 - Scheduled Power Curtailment.

Feb 22, 2026

No incidents reported.

Feb 21, 2026

No incidents reported.

Feb 20, 2026

No incidents reported.

Feb 19, 2026

No incidents reported.

Feb 18, 2026

No incidents reported.

Feb 17, 2026

No incidents reported.

Feb 16, 2026
Resolved - This incident has been resolved.
Feb 16, 05:16 UTC
Update - The site has been re-energized, but a portion remains offline as the transformer repair is still in progress.
Feb 10, 09:44 UTC
Identified - The facility has powered down to address a transformer issue. We will provide an update once the issue has been resolved and the site has been re-energized. Thank you for your patience and understanding.
Feb 9, 15:10 UTC
Feb 15, 2026
Resolved - This incident has been resolved.
Feb 15, 08:03 UTC
Identified - The local power authority has issued a notice to curtail. The mining facility will power down between 6:00 AM to 7:00 AM and 5:00 PM to 6:00 PM Central time, February 13, 2026.

Our technicians will bring miners back online as soon as the curtailment period is complete. Thank you for your patience and understanding.

Feb 13, 07:38 UTC
Feb 14, 2026

No incidents reported.

Feb 13, 2026
Resolved - This incident has been resolved.
Feb 13, 07:37 UTC
Identified - The local power authority has issued a notice to curtail. The mining facility will power down between 6:00 AM to 8:00 AM and 4:00 PM to 7:00 PM Central time, February 12, 2026.

Our technicians will bring miners back online as soon as the curtailment period is complete. Thank you for your patience and understanding.

Feb 12, 07:14 UTC
Feb 12, 2026
Resolved - This incident has been resolved.
Feb 12, 05:44 UTC
Identified - The local power authority has issued a notice to curtail. The mining facility will power down between 6:00 AM to 9:00 AM and 5:00 PM to 7:00 PM Central time, February 11, 2026.

Our technicians will bring miners back online as soon as the curtailment period is complete. Thank you for your patience and understanding.

Feb 11, 06:21 UTC
Resolved - This incident has been resolved.
Feb 12, 05:43 UTC
Identified - The local power authority has issued a notice to curtail. The mining facility will power down between 7:00 AM to 9:00 AM and 6:00 PM to 7:00 PM Central time, February 11, 2026.

Our technicians will bring miners back online as soon as the curtailment period is complete. Thank you for your patience and understanding.

Feb 11, 06:22 UTC
Feb 11, 2026
Resolved - This incident has been resolved.
Feb 11, 02:02 UTC
Identified - The Facility is undergoing routine maintenance. Customers may experience intermittent downtime of a few hours over the next several days.

Thank you for your understanding.

Jan 7, 21:13 UTC
Feb 10, 2026
Completed - The scheduled maintenance has been completed.
Feb 10, 19:00 UTC
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Feb 10, 17:30 UTC
Scheduled - The power provider has scheduled a curtailment today at the following Indiana data centers, in accordance with our contractual agreement with them:
· Indiana 1 (Fulton)
· Indiana 2 (Miami)
· Indiana 3 (Richland)
All listed locations will have a planned outage on 02/10/2026, from 12:30 PM to 2:00 PM EST, lasting approximately 1 to 1½ hours.
We apologize for any inconvenience this may cause and appreciate your understanding as we work to comply with the power provider’s requirements.

Thank you for your cooperation.

Feb 10, 15:08 UTC
Feb 9, 2026