Indiana 1, Indiana 2, and Indiana 3 - Scheduled Power Curtailment

Scheduled Maintenance Report for Compass Mining

Completed

The scheduled maintenance has been completed.
Posted Apr 08, 2026 - 15:10 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 08, 2026 - 10:40 UTC

Scheduled

Our power provider has scheduled a curtailment at the following Indiana data centers, in accordance with our contractual agreement with them:

Indiana 1 (Fulton)
Indiana 2 (Miami)
Indiana 3 (Richland)

All listed locations will experience a planned outage on 04/08/2026 from 06:40 AM to 11:00 AM, lasting approximately 4.3 hours.

We apologize for any inconvenience this may cause and appreciate your understanding as we work to comply with the power provider's requirements.

Thank you for your cooperation.
Posted Apr 07, 2026 - 20:00 UTC
This scheduled maintenance affected: Indiana 1, United States, Indiana 2, United States, and Indiana 3.